Evaluation of different options of upsteam facilities for the co-combustion of selected waste fuels in the power plant Dürnrohr / Austria / 2003
- Contractor:
- End customer:
- Capacity:
- Activities of TBU:
|
EVN Energieverwertung Niederösterreich AG,
A-2344 Maria Enzersdorf
EVN Energieverwertung Niederösterreich AG,
A-2344 Maria Enzersdorf
120 MW (about 150.000 tons per year)
Evaluation of different options of upsteam facilities for the co-combustion of selected waste fuels in the power plant Dürnrohr |
|
|
Waste Incineration Plant Energos Donaustadt / Austria / 2002-2003
- Contractor:
- End customer:
- Capacity:
- Activities of TBU:
|
Siemens AG Österreich, 1210 Wien
Energos ASA, Norway
2 x 26 MW (80.000 tons per year industrial waste)
Engineering and cost estimate for gas cleaning, waste-economical and safety-related expert´s report for environmental impact assessment planning
|
|
|
Evaluation of different treatment plants for ashes from Vienna´s waste Incineration plants / Austria / 2002-2003
- Contractor:
- End customer:
- Capacity:
- Activities of TBU:
|
Magistrat der Stadt Wien, Abt. MA 48, A-1050 Wien
Magistrat der Stadt Wien, Abt. MA 48, A-1050 Wien
20.000 tons of ashes per year
Evaluation of different treatment plants for ashes from Vienna´s waste Incineration plants
|
|
|
Feasibility study for Vienna´s third waste incineration plant / Austria / 2002
- Contractor:
- End customer:
- Capacity:
- Activities of TBU:
|
WKU Wiener Kommunal-Umweltschutzprojektgesellschaft m.b.H.,
A-1110 Wien
WKU Wiener Kommunal-Umweltschutzprojektgesellschaft m.b.H.,
A-1110 Wien
250.000 tons per year
Rough engineering and cost estimate for Vienna´s third waste incineration plant |
|
|
Industrial Waste Incineration Plant Saria Tulln / Austria / 2002
- Contractor:
- End customer:
- Capacity:
- Activities of TBU:
|
EVN Energieverwertung Niederösterreich AG,
A-2344 Maria Enzersdorf
Saria Bio-Industries GmbH, A-3430 Tulln
15- 55 MW
Rough engineering and cost estimate for an industrial waste incineration plant, consisting of fluidised bed incinerator, steam boiler, dry and catalytic flue gas cleaning
|
|
|
Waste Incineration Plant St. Andrä / Austria / 2001
- Contractor:
- End customer:
- Capacity:
- Activities of TBU:
|
Verbund-Umwelttechnik GmbH, A-9020 Klagenfurt
Verbund AG
196 MW
Process engineering, technical tender documents for a fluidised bed incinerator |
|
|
Waste Incineration Plant / Athens / Greece / 1999
- Contractor:
- End customer:
- Capacity:
- Activities of TBU:
|
Lenzing Technik GmbH & Co KG, A-4860 Lenzing
Attika Athen, Greece
150 MW
Concept for a waste incineration plant with fluidised bed incinerator, steam boiler and semi-dry flue gas cleaning |
|
|
Waste Incineration Plant Spittelau / Austria / 1995
- Contractor:
- End customer:
- Activities of TBU:
|
UV&P GesmbH, A-1020 Wien
Fernwärme Wien GesmbH, A-1110 Wien
Consulting for improvement activities, issue of a safety analysis with action plant |
|
|
Waste Incineration Plant Flötzersteig /Austria / 1995
- Contractor:
- End customer:
- Activities of TBU:
|
UV&P GesmbH, A-1020 Wien
Fernwärme Wien GesmbH, A-1110 Wien
Consulting for improvement activities, issue of a safety analysis with action plant |
|
|